Temporary Certificate of Occupancy
A temporary certificate of occupancy may be issued when a portion of a project is
complete but the entire job is not. A temporary certificate allows legal occupancy
of only that area that is stated on the T.C.O. To obtain a T.C.O., the owner or
the permittee is required to complete an application form requesting the T.C.O.
On this form you are required to state the area(s) that will be included in the
T.C.O. You are also required to state the approximate time it will take to complete
the remaining portions of the project.
Only the owner or permittee can request a T.C.O according to Section 110.3 of
the CT State Building Code.
What are the minimum requirements that make a portion of the project eligible for a T.C.O?
Section 110.3 of the CT State Building Code states that the portions of the project
can be occupied "provided that such portion or portions shall be occupied safely prior
to full completion of the structure without endangering life or public welfare."
This means that all safety items or elements of the area to be occupied shall be
completed. This includes all stairs, handrails, guardrails, floor surfaces, alarm systems,
smoke detectors, safety glazing, etc. Also, all electrical work shall be completed to
the point were required elements are completed and all non-required elements are made
safe (no exposed wiring). Hot water shall be provided. From October through April the
heating system shall be operational. Dwelling units shall contain a minimum of a completed
kitchen, living and sleeping areas and one fully functioning compliant bathroom with
a lavatory, water closet and bathing facilities.
The Division of Building Inspection will issue a T.C.O after all the following
have been completed and "signed off":
Field inspections: All projects require final inspections for building, electrical,
plumbing and HVAC. It is the permittee or owner's responsibility to request each of
these inspections. This can be done using the Inspection Request Line (622-7772)
Permit conditions: Permit conditions are checked by office staff for compliance.
Any condition that affects safety in the area to be occupied shall be complied with
prior to issuance of the T.C.O.
Zoning compliance: All T.C.O.'s require zoning approval. Written certification of zoning compliance shall be obtained from the Zoning Enforcement Officer, Planning and Zoning Office, and shall be submitted to the Division of Building Inspection by the permit holder.
Agency approvals: Check with the Division of Building Inspection staff to see
if any of the following Town agency approvals are required. It is the permittee or owner's
responsibility to obtain these approvals from these agencies.
Greenwich Fire Marshal: 622-3950
This office has fire inspectors that will inspect the work done under the permit.
You are responsible for scheduling this inspection directly with the Fire Marshal's office.
When this inspection has been made and approved, the Fire Inspector will notify the Division
of Buildings directly, usually by email. This approval does not apply to one and
two family dwellings.
DPW, Sewer Division: 622-7760
New buildings that are connected to the Town sewer system require an inspection of the
sewer connection by the Sewer Division of the DPW. You are responsible for arranging
for these inspections with the Sewer Division prior to backfilling. After inspection,
you will be issued a Notice of Sewer Connection (Sewer Final). You must submit this
notice to the Building Inspection Division before a T.C.O. can be issued.
DPW, Engineering Division: 622-7767
P&Z conditions often require approval from the Engineering Division prior to T.C.O.
If Engineering approval is required, you are responsible for arranging the inspection
and providing the Engineering Division with any information they need.
After inspection, the Engineering Office will send a memo to the Division of Building
Inspection stating they have no objections to the issuance of a T.C.O.
Health Department,
Division of Environmental Health: 622-7838
All buildings that involve any of the following will require approval from this
Division prior to the issuance of a T.C.O.:
Serving or preparation of food for the public
Buildings that discharge into a private septic system
Buildings that are supplied with water from a well
Irrigation wells
Child care facilities
Cosmetology facilities (nail/beauty salons, etc.)
Variety/food stores (including mini-marts)
Public pools (including private clubs)
This Division will issue a memo to the Division of Building Inspection stating their approval.
It is the responsibility of the permittee to obtain all inspections and approvals from this Division.
Instructions for filling out the application:
Type in the information online, print, then sign - signature is required. The application
can then be faxed (203-622-7848) or delivered to the Building Inspection Division,
Town Hall, 2nd floor.
Application for a Temporary Certificate
of Occupancy
|
|
News & Department Info
Board Information
·Planning & Zoning
Board of Appeals
·Building Code Board of
Standard and Appeals
Permits
Building Inspection
·Information & Hours
·Forms
·Inspections
·Certificates of Occupancy
·Code Questions & Info
·Archives
Building Construction and Maintenance
·Information & Hours
Engineering
·Information & Hours
·Plans, Projects and Bids
·Traffic Signs, Signals and Regulations
·Stormwater Information
·Flood & Erosion Control Board
Highway
·Information & Hours
·Leaf Collection
·Snow Removal
·Animal Disposal
·Call before you dig
Sewer
·Information & Hours
·Private Inflow Removal
·Smoke Testing Program
·Sewer Extension Projects
Waste Disposal
·Information & Hours
·Recycling
·Hazardous Waste Day
·Holly Hill Transfer Station
Report Tree Problems
Report Street Light Problems
Contractor Payments
Related Links
·Police Dept., Traffic Section
·Parking Services Department
·CT Dept. of Transportation
|
 |