black left side border I Want To: Quick Links Link to list of all town departments Link to list of all town services Link to Calendar Link to FAQs Link to Forms Link to Site Tour Link to Contact Us page Link to translation page Link to web resources page Link to Town Employees Link to Town Movies Link to Greenwich Community TV The Greenwich Community Covenant

 

gray ride side border
News:

South Water and Den Lane Force Main Project
South Water Street, North Water Street, New Street, Henry Street and Den Lane between Hollow Wood Lane and Pemberwick Road

Commencing on Wednesday, July 8, 2009 (weather permitting), final road restoration will begin. This will include milling and paving the full width of the road in the following locations:

· South Water Street (between Division and Church Street) heading north to North Water Street
· North Water Street (to the intersection of New Street)
· New Street to Henry Street
· Henry Street through the Byram Road intersection
· Den Lane between Hollow Wood Lane to the intersection of Pemberwick Road

Work will involve temporary single lane closures with alternate two way traffic directed by Police/Flaggers.

This is the final road restoration (paving) that is required to complete the South Water and Den Lane Force Main projects. Work is anticipated to take approximately one (1) week to complete. Striping/pavement markings will be installed shortly after the road restoration is completed, but will performed at night.


gray ride side border Search


Articles

black right side border
black left side border Shadow for footer black right side border
black left side border
Home | Privacy Policy | Help | Contact Us | Site Map | Legal

Town Hall - 101 Field Point Road - Greenwich, CT 06830 - (203) 622-7700

Copyright ©2010, Town of Greenwich. All rights reserved.
black right side border